Quick Menu

Sir Nigel Gresley overhaul – update 16

By |

The team in The Works are pressing on with the overhaul of Sir Nigel Gresley. Locomotive Engineer Darrin Crone provides us with an insight into recent weeks’ work.

This is the 16th update – you can catch up on the previous posts here.


Week commencing 5 May

The reverser clutch has been undergoing refurbishment over the last few weeks and has already received new brake linings. This week we acquired the new rubber diaphragm. To keep production costs down the diaphragms are supplied without holes, so these have to be punched through. Once this was done the clutch was reassembled and can now be refitted to the loco. A spare diaphragm was also obtained, which has been punched and will be put in store.

The clutch grips onto the reversing shaft, which was put up on trestles this week to begin the removal of paint and general cleaning prior to inspection. The end journals were inspected and are round, parallel and showing little wear. The bearings in the brackets on the loco were also inspected. They are in a satisfactory condition and will not require replacement.

The regulator valve overhaul continued this week with the valve seat lapped using a special tool brought from our Grosmont store. Danny Holmes of the National Railway Museum skimmed both the valve and pilot valve to restore their faces, with the latter showing the most wear. The pilot valve was then used to lap the pilot seat in the top of the regulator valve. Inside the valve there are rings that run in an internal bore, which was cleaned before the unit was reassembled. On the bench the travel of the valve was measured and compared to the LNER drawing. It was confirmed that the movement of the operating lever connected to the regulator lever in the cab produces the correct lift of the regulator valve. During the valve rebuild the brackets that support the valve in the boiler and the operating half shafts were dye penetrant inspected and no defects were found. New bolting is required to complete the regulator valve overhaul and it will then be refitted to the boiler.

Painting continued on the inside of the loco frames, behind the buffer beam and on the bogie. The cylinder ends received their first coats of high temperature black and by the end of the week the bogie was receiving undercoat. Before painting began on the top of the bogie, Alan Pitt dye pen inspected the welds around the sections added to the bogie centre casting and to an old weld repair. No faults were found.

The bogie centre casting that sits between the bogie stretcher on the loco and the centre casting in the bogie frames received dye penetrant inspection this week. There is more to do on this part and it will need a comprehensive dimensional inspection to determine why it shows uneven wear. Our CME completed his dimension inspection of the bogie frames this week.

The top of the bogie centre casting that slides from side to side in the bogie. The loco pivot pin goes down the centre hole.

The position of the refurbished combined spring and brake shaft bracket was confirmed on Tuesday before new fixing holes were drilled through. After last week’s disappointment with the breaking of the cutter on the first hole, it was not without trepidation that the mag drill was started and the cutter entered its first hole. However, the drilling went well and the same cutter managed to drill all the fitted bolt holes. In addition to the bolt holes, two smaller rivet holes were drilled through in stages using standard drills. Four of the old fitted bolts were machined as clearance bolts and have been used to clamp the bracket in place. The bolt holes will need reaming and new bolts making, but first the back of the bracket will require countersinking for the rivets and spotfacing for bolting where the holes are near to the welds.

The holes for the mounting of the leading right-hand combined brake shaft and spring bracket were drilled through this week. Malcolm Bateman supervises as John Livesey feeds in the cutter.

The two loco brake shafts were moved to near the bogie for inspection and refurbishment. While taking the paint off the trailing shaft we discovered that it is marked 4901. There was an A4 numbered 4901, named Capercaillie, which became BR 60005 Sir Charles Newton.

The loco brake shafts are now being refurbished. The trailing shaft has the long arm laying on top of the leading shaft.

The long arm on the trailing shaft is marked 4901.

Reinstalling pipework between the frames continued this week with the refitting of the couplings that connect the axle box lubrication hard pipes to the hoses joined to the coupled wheel axle box underkeeps. The steam sands supply pipe was cleaned, annealed and refitted between the tee on the stretcher between the sand boxes and the Cartazzi frames. The pipes to the vacuum clutch and the last remaining copper pipe for the axle box lubrication system were also retrieved from store this week. Cleaning and annealing of these pipes began.
The boring of the cylinder mounting holes continued, but as the job gets harder the progress slows. After a number of modifications to the jig, the last and most inaccessible hole has been bored through. Before work stopped last Thursday, the last finishing cut was just short of breaking through.

We are planning to remove the accommodation bogie and support the front of the loco frames on our new screw jacks. This will enable the loco bogie stretcher and lower outside cylinder bolts and studs to be examined. To use the jacks we need a beam for them to stand on, since we are over a pit and the distance over the frames is within rail gauge.

The screw jacks under the front of the loco frames will take the weight of the frames when the accommodation bogie is removed.

We were given surplus steel beam by Simon Holroyd and two lengths were cut to size. Some steel packing was required to make them level with the rail head and this was cut to size before the assembly was welded together. After grinding to ensure a good fit between the rails, the beam assembly was lowered into position with the crane. The jacks were then put in position ready for the lift. The bogie pivot pin was also removed so that the frames don’t have to be lifted so high to clear the accommodation bogie.

The bogie pivot pin was removed this week. The nut is at the lower end of the pin.

The valve chests that require new liners have now been measured by the supplier and the liners will now be finish machined. When they are finished, fitting will be organised.

Not mentioned in the report, but a special new thread stud had to be manufactured for the manifold. This is shown fitted in the centre top hole. The manifold shut-off valve has been repacked and the overhaul of this assembly is now complete.

 

Week commencing 12 May

We started the week with the lifting of the loco and the removal of the accommodation bogie. It had been planned to move the bogie clear of the front of the frames, but in the end we decided to move the bogie into the trailing bogie wheel cut-out in the frames, just to the rear of the cylinders. This meant that we didn’t have to lift the frames so high and we don’t use up valuable space in front of the loco. When packing is added to the top of the accommodation bogie, it will also act as an additional support. The available space was measured to make sure it would fit and would not hinder work on the frames. The team lifted the engine using jacks on the front bufferbeam, ensuring we had a level lift, and followed the lift with the screw jacks. When lifted sufficiently high to clear the spigot on the loco’s bogie stretcher, the bogie was pushed back and the loco was then lowered and the frames levelled.

The loco frames being lifted to allow the removal of the accommodation bogie that has been supporting the front end. Bob Shearman operates the jack while Andy Barwick checks to see the gap between the loco and the accommodation bogie.

The front of the frames are now supported by screw jacks.

We can now access the bogie stretcher on all sides, so cleaning has begun. There is still some time to be spent on this, then the paint will be stripped off and the stretcher will be examined. The stretcher not only loads the bogie but also ties the outside cylinders and frames together.

With the accommodation bogie removed we now have access to the bottom of the loco bogie stretcher and pivot.

With the accommodation bogie removed the bolts that run through the bogie stretcher, frames and outside cylinders can be accessed. The right hand cylinder is the only one marked LNE and may be the original fitted at Doncaster during construction.

Painting continued on the loco bogie and the expansion link brackets with the application of top coats. We are painting these brackets now, as they won’t be so accessible when the reversing shaft is refitted. The reversing shaft has now been thoroughly cleaned, with all paint removed by needle gun. The end threads and key ways were degreased and dye pen inspection has now been completed. After painting the shaft will be ready for reuse. The brake shafts have also now been finish cleaned and await inspection. The loco brake hangers were removed from the loco after trial fitting and have been cleaned and needle gunned prior to refurbishment.

The inspection of the reverser shaft has now been completed.

The reverser shaft is marked with Sir Nigel Gresley’s original LNER number 4498.

The loco brake hangers have been trial fitted and show wear that will have to be repaired. Prior to this work they were needle gunned by Peter James to remove old paint so that any hidden faults can be found.

The new seals for the brake cylinders have arrived and await refitting. The seals under the piston rod cover plates were replaced. The leading cylinder mounting brackets were retrieved from store and their fit on the leading cylinder mounting trunnions examined. There is noticeable heavy wear on the trunnions and the centre bracket which will require repair.

New cylinder cover studs were fitted to the middle cylinder this week and the old ones removed as life expired. Some of these studs go into steam spaces so they were sealed in. All studs now run out of thread on their shanks as previously some of the old ones bottomed out.

Work on the refurbished combined brake and spring bracket continued with reaming of the fixing holes. All holes have now seen the reamer, though a couple still need some further work. A plan for spotfacing and countersinking the back of the bracket has been devised and tooling is now being sought.

The boring of the leading top cylinder mounting holes has been completed and the last two holes that could not be accessed by a reamer have been honed. The job has now been reviewed and since the honed finish is impressive, it has been decided that another day should be spent with the hone to clean up the other holes before they are measured for new fitted bolts.

The last axle box hard pipe was annealed and fitted this week before work moved on to start the refurbishment and refitting of the vacuum clutch pipework.

Progress on the boiler at Llangollen has now started with the removal of stays in the back corners of the firebox. They have not caused us any problems but are to be replaced as a precautionary measure due to age and their position in a stressed area. The leading sling stays that support the firebox crown have been removed to enable the new tubeplate to be fitted. The new tubeplate is now complete and is ready for our inspection at LNWR Crewe.

Inside the boiler the sling stays are being removed. This will allow the crown plate flexibility to enable the fitting of the new tubeplate.

Written by Harriet Cash

Categorised As:

Tagged As:

Leave a Comment

Your email address will not be published.