Quick Menu

Sir Nigel Gresley overhaul – update 17

By |

The team in The Works are pressing on with the overhaul of Sir Nigel Gresley. Locomotive Engineer Darrin Crone provides us with an insight into recent weeks’ work.

This is the 17th update – you can catch up on the previous posts here.


Week commencing 5 June

The steam cylinder off the air pump was finish machined last week but the bore still needed to be cleaned, so it was polished and honed this week and reassembled to the low-pressure air cylinder with the piston rod and pistons in place. The rod that controls the admission of steam to either side of the steam piston was trial fitted with the top end cover in place to check the travel of the pistons and rod, and all seems to be in order.

The major components of the air pump are now being reassembled. The steam cylinder is to the right and the low-pressure air cylinder to the left.

Last week we made a start on the spotfacing of the right-hand leading combined brake shaft and spring bracket mounting holes, using burrs to remove the first material. This week the spotfacing tool was applied and two holes were finished.

Two spotfaces were cut on the right-hand combined brake shaft and spring bracket. The welds on this fabricated bracket are larger than the radius in the corners of a casting, so they have to be cut in two to provide a clamping face for the bolt that will be fitted into the hole.

Cleaning of the coach dynamo continued this week. According to British Rail instructions, it should be wire brushed and given another coat of bitumen. However, having been subject to this regime, the coating was coming off in thick pieces and the surface of the dynamo showed corrosion, so we decided to take it back to a sound surface and give it a coat of primer. We didn’t want to apply bitumen during overhaul and testing, when it has to be manipulated. The stripping was also finished this week and a coat of primer applied. The seal under the domed end cover was also cleaned out so that we are sure of a good weatherproof seal.

All the parts of the coach that are going separately for overhaul have now been prepared, and collection has been organised with the contractor.

The reverser shaft key has been repaired and fitted, and is now a good fit in both the shaft and the reverser lock sheaves. The special eyebolt that fastens the reverser spring to the vacuum clutch frame stretcher has also been refurbished. The reverser spring is fractured so a new one is needed. We have contacted a number of specialist spring manufacturers are awaiting quotes.

At Llangollen we had a very productive meeting with the body responsible for our mainline certification, our insurers and the Llangollen engineering team. The method of preparation for the fitting of the new tubeplate has been agreed, and involves the refurbishment of the combustion chamber plates. We also measured the combustion chamber opening to assess how much distortion there is, and therefore the amount of movement required from the plates to contact the new tubeplate. We were pleased that there is sufficient room to get the new tubeplate in comfortably without requiring a lot of movement from the old plates. This should give us the best possible fit.

The right-hand outer wrapper has now been riveted along its trailing edge to the outer doorplate. The sides are drilled to tapping size.

The roof stays were also examined with our own endoscope. We had a close look and concluded that most of the roof stays will be suitable for further service. However, we agreed that some stays will be removed and their condition assessed. We also agreed that the outer rows of side stays be ultrasonically tested to ensure there are no undiscovered fractures in these areas.

In the Llangollen boiler shop. Darrin Crone views images of the roof stays taken by the endoscope, operated by Paul Aston, engineering team member, on the right.

An image taken of a roof stay by the endoscope. The thread on the end of the stay goes into the firebox crown sheet. The condition of this stay, appears to be very good and it looks to be suitable for further use, however some stays will be removed to examine their condition inside the plate.

After our visit to Llangollen we went on to Crewe to inspect the new copper firebox tubeplate. It is a very good piece of work and corresponds to the drawing and our instructions. When we receive the final documentation for the plate we will organise transport to Llangollen.

The finished copper tubeplate at Crewe with inspection documents during final examination and acceptance by Sir Nigel Gresley Engineers.

Work between the frames on the lubrication piping continued this week with some finishing touches to the axlebox lubrication system. On Wednesday, the cylinder lubrication pipework was retrieved from store. It was then flushed through and the pipes cleaned. The pipes are now ready for annealing and fitting. Meanwhile, work continues off site on the cylinder lubricator.

The refurbishment of the pistons was completed this week and, after inspection at our suppliers, are now ready to be returned to York.

Work continued on the loco’s bogie stretcher this week with further cleaning and the removal of most of the paint. This will allow detailed inspection. The lubrication fittings have now been removed from the stretcher and it appears that water has been passing one of the fittings. This would find its way onto the bearing surfaces between the loco and bogie, and we think this explains the uneven wear we have found. The wear could not be explained by uneven loading, as the positions of the bearing surfaces relative to each other have been measured and all seems to be in order. We have now agreed a plan for refurbishment of the bearing surfaces.

The underneath of the loco bogie stretcher has now been cleaned, though a little work is left to do.

Not mentioned in the report, the safety valves were retrieved from store this week. They will be stripped and examined for condition.

Also not mentioned in the report, the coupled wheel axle boxes are being put on the marking-out table at the National Railway Museum. The disc in the centre is exactly the same size as the axle journal that runs in this bearing. Measuring from the centre of the disc allows the position of the axle on the locomotive to be calculated. This is important, as the centre dimensions will need to be known accurately when the axleboxes are re-metalled.

Week commencing 12 June

On Tuesday the air brake components, voltage regulator and dynamo removed from the coach were collected by Rampart, our coach chassis overhaul contractors. It is planned that the coach will follow in early July. The air brake distributor mounting manifold and the fittings recovered from the other air brake components were refitted to the coach and were sealed with duct tape.

One of the vacuum brake cylinder connectors. It has been cleaned and dressed with the attachment flange flattened to provide a good seal on the cylinder

The loco brakeshafts were dye penetrant inspected this week and no faults were found.

The leading brake shaft was put up on a trestle for di-pen inspection

We have now received the final documentation for the new copper tubeplate so it can leave Crewe. Llangollen Railway Engineering are now organising collection and delivery to their works. At Llangollen the stays have been removed from the throat plate and backhead where sections of plate above the foundation ring was found to be grooved and was removed. The steam supply pipe from the backhead to the internal manifold has also been removed to repair the joint in the backhead pad. This had been a source of problems in the past so the joint will be refurbished. The combustion chamber and back corner stays we decided to renew at this overhaul have now all been removed and the holes will now be reamed.

Work continues on the loco bogie stretcher with removal of the loco bogie side bearers that stop excessive rolling of the loco. The side bearers are in need of refurbishment and will require new bolts. The cleaning of the underneath of the stretcher continued this week and was completed after some needle gunning under the left hand cylinder before the Painting Team were sufficiently satisfied with the level of cleanliness. The top of the stretcher also saw the needle gun this week and the final traces of scale being removed.

The left loco bogie side bearer bolted through the bogie stretcher, frames and outside cylinder. A view from the inside looking on the bogie stretcher flange

Above the loco, bogie stretcher work continues on the bolt holes that go through the saddle and middle cylinder. The top of the the holes are finished but the bottoms, hidden under a flange require attention. We need to spotface these holes however the location and proximity to the side of the casting is giving us problems.

Areas receiving top coats of paint this week included inside the space between the front bufferbeam and cylinders. The reversing shaft is now up to undercoat.

The air pump reassembly continued this week with the addition of the high pressure air cylinder and end covers. The pump was laid on the surface table so that the mounting brackets on the steam cylinder and low pressure air cylinder could be accurately aligned. The air pump was lifted in to position on Thursday and fits very well on to the mounting plate in the frames without the use of shims previously used under the mounting brackets.

The air pump was put up on the surface table in the NRM Workshop to ensure it would fit flat on the loco mounting plate. Roger Turnbull checks for tightness in the bolted joints before fitting to the loco

The air pump steam inlet flange required new studs and these we made and fitted this week. An order has been placed for new loco and bogie spring hanger bolts and material has now arrived at our contractors and we have received the material certification.

The air pump in position on the loco frames

The outside crankpins in our centre coupled wheels have now been removed at Buckfastliegh. The wheelset has been put on the “quartering” machine and the machining of the crankpin holes is underway. The material for the crankpins has been cut and machining of the pins has started.

The safety valves have now been stripped and inspected. The rear valve sees little use as the leading valve is set to blow at a lower pressure. As the leading valve does by far the most work it has worn and we think it’s time to replace it. The trailing valve, apart from some external marking, is in very good condition, though will require a new spring.

The front safety valve laid out for inspection. It shows erosion in the bottom flange and in the top cover where steam at 250 pounds per square inch ferociously rushes through when it blows

The hose connectors to the leading vacuum cylinders were retrieved from store this week and trial fitted to the cylinders. When tried in place it was found that their mounting flanges were not flat, probably from being clamped on to thick soft seals. They were skillfully hand fitted this week and they are now sit flat onto the cylinders.

Another part retrieved from store and receiving attention is the regulator stuffing box which sits on the boiler backhead in the cab. It takes the shaft that runs between the regulator handles and encloses the joint between the shaft and the rod that goes in to the boiler to the regulator valve. A start has been made on the removal of the life expired studs.

The final journal centre dimensions have been taken from the coupled wheel axleboxes. All six boxes have been done so that they can now be transported to our contractors for remetalling.

We plan to dispatch the superheater header for refurbishment on the road transport that returns our pistons. We have carried out some work on the header, as the more we do using the Engineering Team the less there will be for the contractor, and this will reduce the cost. This week we began to remove the seal-welded plugs in the ends of the header. The plugs give access to enable expanding the outer rows of superheater element tubes. The Engineering Team started the removal by drilling through the plug centres.

The end plugs in the superheater header are in the process of being drilled through

Not mentioned in the text, one of the leading vacuum brake cylinders on the NRM Workshop Union borer. The trunnions show wear and are to be skimmed and re-sleeved. We have LNER/BR documentation showing this permitted repair procedure

Written by Harriet Cash

Categorised As:

Tagged As:

  1. Andrew Dolan

    Fantastic work going on there, extremely thorough. Well done all concerned, look forward to seeing her out and about soon.

  2. John Snow

    Very interesting indeed; after all these years, it is still an amazing sight to see those components on view. The safety valves were impressive and the endoscope picture was great too. Thanks and good luck with the overhaul.

Leave a Comment

Your email address will not be published.